PHYSICAL PLANT SHOPS AND CENTRAL STORES

Central Stores, Physical Plant

Built: 1933

Addition: 1936-37, 1971-73

Architect: 1933, 1936 - A.H. Kimball, 1971 Woodburn & O'Neil

Contractor: 1933 Kucharo Const. Co., 1936 Ben Cole & Sons, 1971 Mueller Const. Co.


At the Board meeting of April 26, 1933, President Hughes made the following recommendation which was approved and referred to the Special Building Committee with power to act:

I recommend that $30,000 of the Book Store fund be spent in the erection of the first unit of the Central Stores Building, this building to be of the simplest possible construction of brick and concrete and having two stories and a basement, the floor of the first story to be on a level with a truck bed so that material can be loaded in and out most readily. The erection of this building will free the rear of Botany Building from use as a store room and would thus make available some very much needed space for the Botany Department. It would also make possible the consolidation of two store rooms and save some money in help. There are many other advantages in this arrangement, and I hope the Board will approve this recommendation.

It seems probable that the preliminary plans had been developed prior to that date since construction bids were received on June 27, including an alternate proposal to omit the three south bays. A contract was awarded on the basis of the smaller size building. The mechanical and electrical work was to be provided by the Buildings and Grounds Department.1

When excavation was made for the foundations a layer of quicksand was encountered. This resulted in a change in footing design and a separate contract for the additional labor and material, in the amount of $3258.15, was negotiated with the contractor for the extra costs.2

Construction was completed and the project accepted in November 1933. In 1936 a grant of $13,500 from the Federal Emergency Administration of Public Works, together with a State appropriation of $16,500, made possible the construction of a south addition to the Central Stores Building. Contracts were awarded in September and the building was completed and accepted on January 30, 1937.3

This building became the headquarters for the Buildings and Grounds Department (later Physical Plant Department) as well as for Central Stores.

Minor remodeling in 1958-59 added about $7500 to the building valuation and included construction of a covered dock on the east side.4

Long-range planning to replace the numerous small, outmoded buildings in the Physical Plant service area with new facilities is first recorded in the Iowa State Daily for December 10, 1960: “The old buildings around the physical plant will be removed and adequate buildings constructed.” By 1963 the plans were somewhat more developed: “The expansion of physical plant shops and stores will provide additional shop space for the University’s maintenance force, additional storage space for maintenance materials, and garage space for the storage and servicing of University-owned vehicles.”5

An appropriation of $1,000,000 for Physical Plant Shops and Stores was requested in 1966 and in subsequent years, but it was 1971 before funds were made available for construction. The architect had been retained in 1968 to enable plans to be prepared so that bids could be received and construction started at the earliest possible date. 6

The schematic drawings for the proposed building were approved by the Board as recorded in the Minutes of the January 14-15, 1971, meeting when the following project description was presented:

The proposed building will house all Physical Plant Shops and Central Stores Warehouse facilities and Central Receiving, as well as Physical Plant and Purchasing Department administrative offices. It will replace eleven miscellaneous outdated and inefficient buildings.

New construction will consist of a “U” shaped one-story structure with full ground floor in the shops wing and partial ground floor in the warehouse wing. This building will abut the existing Central Stores and Physical Plant office building which will be renovated to accommodate all administrative office functions of the Physical Plant and Purchasing Departments. The new structure will be of steel framing with a composite steel and concrete floor system and exterior walls of precast concrete and metal siding.

Bids for the construction of the new building were received and contracts awarded in October 1971.7 The project was completed and occupied late in 1973.

  1. Minutes, June 28-29, 1933 ↩︎

  2. Minutes, October 11, 1933 ↩︎

  3. Minutes, February 25, 1937 ↩︎

  4. Iowa State Daily, November 7, 1959 ↩︎

  5. Iowa State Daily, November 14, 1963 ↩︎

  6. Minutes, September 12-13, 1968 ↩︎

  7. Minutes, October 13-15, 1971 ↩︎